Medical Rehabilitation -Crisis Residential Home
13,275 Sq Ft
Here is a brief scope of work:
General Conditions
– Includes Temp Power and Lighting
– Includes necessary 3rd Party Inspections
– Includes necessary Asbestos Testing
– Site Bathrooms
– Site Security including temp boarding up of walls
– Final Cleaning
Demo – Concrete Cutting, Demo & Haul Off for Plumbing Install up to 200’
– Concrete Cutting, Demo & Haul Off for Electrical Install up to 60’
– Concrete Cutting, Demo & Haul Off for ADA work Approx 4000 Sq ft
– Demo all HVAC ducting – preserve all penetrations for re-use
– Demo HVAC units per plan
– Demo Electrical to sub and panels
– Demo Existing Exterior Windows, Doors and Walls per plan
Concrete – Pour Back for Plumbing Install up to 200’
– ADA Concrete, all flatwork, ramps and sidewalks per plans
– Pour Back for Electrical Install up to 60’
Metals – Metal stud framing all interior walls
– Metal stud frame to underside of existing joist .
– Cut in Pedestrian Gate at front entrance at path of travel and include a
crash exit bar and correlating security features.
Wood, Plastics and Composites
– Supply and Install 15′ of new ADA cabinet upper and lowers at Group
Room 101
– (15) Single Closet Shelves and Closet Poles
– Supply and Install 44′ of new ADA cabinet upper and lowers at Kitchen
– Suppy and Install an 8’x6′ Island
– Supply and Install a built in pantry with cabinets and shelving around
– Supply and Install 8′ of new ADA cabinet upper and lowers at
breakroom
– Frame all New windows and Doors and in-fill per plan
– Frame all new structural for HVAC per plan
Thermal and Moisture protection
– Roof patch for exhaust and unit penetrations per plan
– Caulk and seal all exterior openings
– Provide Weather stripping at all exterior doors
– Insulation as needed per plans
We recently completed this project 9-8-20 Our client was extremely happy. They are giving us 2 more to quote.